LRB lead rubber bearing construction method

 Construction preparation

Check whether the specification, model and quantity of LRB lead rubber bearing meet the design requirements, and whether the appearance has defects such as damage and deformation.
Prepare tools and equipment required for installation, such as crane, jack, wrench, level gauge, etc.
Clean the top surface of the bridge pier and abutment to ensure that it is flat, clean and free of oil stain, debris, etc.


LRB lead rubber bearing installation
Lift the LRB lead rubber beam slowly to the installation position on the top surface of the pier and abutment with the crane. During hoisting, it shall be kept stable to avoid collision with pier and other objects.
The position and elevation of LRB lead rubber beam shall be adjusted so that the center position overlaps with the design position and the top elevation meets the design requirements. Jacks, spirit levels and other tools can be used for adjustment.
When the position and elevation of LRB lead rubber beam are adjusted, use connecting bolts to fix it with the top surface of pier and abutment firmly. The bolts shall be tightened symmetrically and uniformly to ensure uniform stress on LRB lead rubber beam.
1. Assemble the lower and lower connecting plates, LRB lead rubber beam and upper embedded parts on the ground;
2. When the concrete of substructure reaches the design strength of 75, the screw holes of embedded parts shall be cleaned and coated with grease, and then grease and felt shall be used as an isolation layer to prepare for future replacement.
3. Lift it in place according to the LRB lead rubber beam layout plan No.
4. Fix the lower connecting plate firmly on the lower embedded parts with high-strength bolts.


Installation quality inspection
Check whether the installation position of LRB lead rubber beam is correct and whether the appearance is damaged or deformed.
Check whether connecting bolts are tightened and gaskets are complete.
Use a level to measure the top elevation of LRB lead rubber beam to see if it meets the design requirements. In case of any deviation, it shall be adjusted in time.
Measure the center position of LRB lead rubber beam with total station to see if it is consistent with the design position. Any deviation shall be adjusted.
Follow-up work
When LRB lead rubber beam is installed, it shall be protected from collision, pollution, etc. It can be surrounded by protective barriers or covered with protective materials.

The original website of the article: https://www.seismic-isolation-bearing.com/lrb-lead-rubber-bearing-construction-method/

Comments

Popular posts from this blog

Understanding Asbestos Sheet: A Comprehensive Guide

Asbestos sheet , also known as asbestos rubber sheet, is a versatile material composed primarily of asbestos fibers, rubber, and various fillers. This combination results in a durable and resilient sheet that finds extensive application in industrial settings. Asbestos, a naturally occurring mineral, is known for its heat and fire resistance. When combined with rubber and other materials, it forms a composite that retains these properties while adding flexibility and durability. The resulting asbestos sheet can withstand high temperatures and pressures, making it ideal for use as a sealing material in various industrial applications. The manufacturing process involves compressing the mixture of asbestos, rubber, and fillers into sheets of varying thicknesses. These sheets can be cut and shaped to fit specific requirements, making them highly adaptable for different uses. For instance, asbestos sheets are commonly used as gaskets, packings, and seals in pipelines, valves, and other equi...

Top 5 Benefits of PTFE Packing Seals for Extreme Temperature Applications (2025 Guide)

"PTFE seals revolutionized our turbopump operations during Artemis V testing last June," says Dr. Lu- an engineer working at Hengshui Hongwo , Senior Materials Engineer at Lockheed Martin. "They withstood 650°F cyclic loads that destroyed traditional materials in 72 hours." Field Engineer's Tip: When installing in cryogenic valves, always pre-compress seals at 20% higher than operating temeprature (common oversight in field maintenance). Use torque wrenches calibrated to ISO 6789-2017 standards. 1. Unmatched Thermal Cycling Stability PTFE packing maintains 98.7% seal integrity after 5,000 thermal cycles (per ASTM F1467-2024 testing), far outperforming graphite alternatives. This 热循环稳定性 proves critical in aerospace thrusters that swing from -320°F (liquid hydrogen temps) to 1000°F during operation. The secret? PTFE's unique molecular structure "unfolds" during expansion yet recovers shape—like memory foam for industrial seals. 2. Creep Re...

How to cut fiberglass grating

  Straight Cutting Straight cutting is the most common way to process glass fiber reinforced plastic  grating . It is mainly suitable for straight edge trimming or cutting to specific sizes. There are many methods of straight cutting, including the following: Mechanical cutting: This method uses tools like a ceramic disc or a diamond grinding wheel. It uses mechanical equipment for cutting. This method is efficient. It has smooth, sharp edges. It is widely used in industry. When operating, ensure the cutting machine is secure. Set the cutting speed to avoid vibration and heat, which can affect quality. Manual cutting: Use a common steel saw blade for manual cutting when conditions are limited or for small batches. Manual cutting is less efficient. But, it is highly flexible. It is suitable for on-site temporary work or small-scale production. When cutting, keep the saw blade sharp. Apply even force to ensure a smooth edge. Curve Cutting Curve cutting mainly processes complex s...